Nighthawk Substation Conditional Use Permit

Description

A 345/120-kV substation serving Microsoft's data center campus and Greenlink, approved 3-2 with a 14-foot wall, noise limits, and fire plan conditions.

Impact summary

Expands Microsoft's Silver Springs electrical infrastructure with added screening.

Applicant

Name
Microsoft Corporation
Address
1200 W US Highway 50, Silver Springs (portion APN 015-141-13; 018-551-03,04; 018-552-01,02)

At a glance

Hearings
1
Public comments
0
Total mentions
1

Last vote

Approved4–1

Last discussed Mar 5, 2026.