NV Energy wants a CUP for three 345-kV transmission lines spanning ~103 miles across 26 parcels from the Walker River Substation to south of Highway 50. The commission recommended approval 3-2 with detailed conditions on roads, floodplain, lighting, and drainage.

Impact summary

Construction expected fall 2026 through spring 2027; closest homes within roughly a half mile in Stagecoach, which has residents worried about views, drainage and flooding.

Applicant

Name
NV Energy
Address
Walker River Substation, Mason Valley to south of U.S. Highway 50, Dayton

At a glance

Hearings
2
Public comments
10
Total mentions
2

Last vote · County Commission

Approved5–0, unanimous

Last discussed Jul 2, 2026.

We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.

The weekly brief for Lyon County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.