Medium PriorityWater Utilitiesopen

Rolling A wastewater plant expansion delays

Summary

The Phase 4 expansion of the Rolling A Wastewater Treatment Plant needs 31 to 46 more days to finish due to scope changes and weather-dependent work, plus up to $112,000 more in engineering costs (mostly reimbursable).

At a glance

Total mentions
1
Last 30 days
0

Last discussed Apr 2, 2026.

Impact analysis

💰Financial impact

Up to $112,000 from the Dayton Sewer Fund, with about $90,400 expected to be reimbursed.

✅Who benefits

Dayton sewer customers get a completed, properly tested expansion.