Mesquite Boulevard mill-and-overlay and road projects
Summary
City staff provided construction updates on the Boulevard project, noting that manhole raising and nighttime gutter sweeping are wrapping up. Additionally, paving on Leavitt Lane was completed, with drainage work and striping underway before it reopens.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Apr 21, 2026.
Impact analysis
Funded through existing capital improvement allocations.
Local motorists and residents utilizing the Boulevard and Leavitt Lane corridors.
Drivers experiencing minor temporary traffic delays during final construction phases.
Mentions & discussions (2)
Technical Review Meeting - Apr 21, 2026
City staff provided construction updates on the Boulevard project, noting that manhole raising and nighttime gutter sweeping are wrapping up. Additionally, paving on Leavitt Lane was completed, with drainage work and striping underway before it reopens.
City Council Meeting - Feb 10, 2026
The repaving from the Casablanca to Sand Hill continues, with the Levitt/Hafen road project delayed to mid-March by a box culvert supplier strike. The new Falcon Ridge/Hardy Way signal is now live.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Mesquite
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.