Wastewater plant and Apex/Garnet Valley build-out
Summary
The water reclamation facility handled 7.6 billion gallons in 2025 with zero permit violations. Huge wastewater infrastructure is being built out at Apex/Garnet Valley — 43 miles of sewer line the city will own, with first flows expected in 2029 and plant expansion to 75 MGD by 2040.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 3, 2026.
Impact analysis
Major capital investment underway; SNWA is funding design and right-of-way for the Apex sewer connection system.
Industrial development at Apex and future growth citywide get the wastewater capacity they'll need.
Mentions & discussions (2)
Utility Advisory Board Meeting - Nov 3, 2026
The water reclamation facility handled 7.6 billion gallons in 2025 with zero permit violations. Huge wastewater infrastructure is being built out at Apex/Garnet Valley — 43 miles of sewer line the city will own, with first flows expected in 2029 and plant expansion to 75 MGD by 2040.
Trump signs bill to free Apex land in North Las Vegas for development
Trump signs bill to free Apex land in North Las Vegas for development KSNV
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for North Las Vegas
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.