10 issues in water utilities
Highway 50 Sewer Replacement Phase 2
Construction ran 48 days long and hit bad soil and old pipes, so the county added $88,800 to Lumos's oversight contract.
Silver Springs wastewater SCADA failure
Lightning strikes fried the treatment plant's control system, forcing the county to accelerate a $160,216.25 replacement contract with Sierra Controls that was planned for later this fiscal year.
Greenlink West transmission lines through Lyon County
NV Energy is extending about 10 miles of 345-kV transmission lines toward the Storey County line as part of a statewide grid project required by 2028. Construction this fall could bring 200-400 workers; lines will pass near a Stagecoach neighborhood on Annette Avenue with required mitigations.
Creation of the North Lyon Power General Improvement District
A draft service plan is complete for the proposed North Lyon Power GID; a public hearing is set for May 13 at 9:00 a.m.
Dayton sewer capital needs and rate review
Dayton Sewer is budgeted for major projects including the Aspen Creek RIB expansion ($2.5 million placeholder) and needs a master plan update. Staff warn the fund could theoretically run out of cash in two to three years on capital projects, and a rate increase may be coming.
Willowcreek GID rate increase under consideration
The tiny Willowcreek water and sewer district (~300 users) hasn't raised rates in years and may need an interim increase soon — its capital plan includes a treatment plant upgrade and a nearly 20-year-old generator nearing end of life.
Rolling A wastewater plant expansion delays
The Phase 4 expansion of the Rolling A Wastewater Treatment Plant needs 31 to 46 more days to finish due to scope changes and weather-dependent work, plus up to $112,000 more in engineering costs (mostly reimbursable).
Silver Springs GID sewer service expansion
The GID approved adding one NVLCO parcel to its sewer service area — domestic waste only, 6,825 gallons per day peak flow, with the petitioner buying the connection rights.
Rose Peak water main replacement
The county committed up to $249,927 more to finish design and permitting of the EPA-funded Dayton water main, plus a staging agreement with Calvary Baptist Church.
Yerington water rights and rate relief
The temporary water use agreement brings over $600,000 in reservation fees plus up to $375,000 in pumpage fees to the city, which faces a million-dollar water and sewer deficit. Without it, 2,100 users could see roughly $700-a-year rate hikes.